EstatePass
Business & FinanceRegulationseasy15% of exam part

A building permit application is submitted on Monday. According to typical Florida building department requirements, what is the maximum time allowed for initial plan review?

Correct Answer

B) 30 business days

Most Florida building departments are required to complete initial plan review within 30 business days of receiving a complete application. This timeframe may vary by jurisdiction but 30 days is the typical maximum allowed under state requirements.

Answer Options
A
20 business days
B
30 business days
C
45 business days
D
15 business days

Why This Is the Correct Answer

Florida building departments are typically required by state law to complete initial plan review within 30 business days of receiving a complete application. This 30-day timeframe is established to ensure timely processing while allowing adequate time for thorough review of construction documents. The timeframe begins when all required documents and fees are submitted, not when an incomplete application is first received. While some jurisdictions may have shorter internal goals, 30 business days represents the standard maximum allowed under Florida requirements.

Why the Other Options Are Wrong

Option A: 20 business days

45 business days exceeds the typical maximum timeframe required by Florida law. This extended period would generally not be acceptable under standard state requirements for initial plan review.

Option D: 15 business days

20 business days is shorter than the standard maximum timeframe established by Florida requirements. This might be an internal goal for some departments but not the regulatory maximum.

Memory Technique

Think '30 days hath September' - 30 is a common monthly timeframe that's reasonable for thorough plan review without being excessive

Reference Hint

Florida Building Code, Administrative provisions, or local building department procedures manual - typically found in Chapter 1 of the Florida Building Code

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.