A contract says the contractor will obtain permits, but the project manager asks the owner to handle them after signing. What should document the shift?
Correct Answer
B) Written change.
Changing permit responsibility should be documented in writing because it changes the agreed contract duties.
Why This Is the Correct Answer
Changing permit responsibility should be documented in writing because it changes the agreed contract duties.
Why the Other Options Are Wrong
Option A: Add the license number.
Add the license number. skips the written authority, scope, price, notice, or release control needed for permit responsibility.
Option C: Allowance reconciliation.
Allowance reconciliation. skips the written authority, scope, price, notice, or release control needed for permit responsibility.
Option D: Approval came late.
Approval came late. skips the written authority, scope, price, notice, or release control needed for permit responsibility.
Memory Technique
When changing clashes with documented, let the contract speak before Reconciling Starts.
Reference Hint
Study anchor (closed-book): memorize Permit responsibility from CSLB 2026 Law Book; CSLB Home Improvement Contracts / B&P Code Section 7159 cited compliance rule order requirements; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?
