A subcontractor is paid in full for final work and provides a release. Which status should the contractor avoid using before payment is actually received?
Correct Answer
D) False unconditional.
A release should not falsely state unconditional payment status before the payment condition is satisfied.
Why This Is the Correct Answer
A release should not falsely state unconditional payment status before the payment condition is satisfied.
Why the Other Options Are Wrong
Option A: Notice to owner.
Notice to owner. skips the written authority, scope, price, notice, or release control needed for mechanics lien release status.
Option B: Owner-approved substitution.
Owner-approved substitution. skips the written authority, scope, price, notice, or release control needed for mechanics lien release status.
Option C: Payment is front-loaded.
Payment is front-loaded. skips the written authority, scope, price, notice, or release control needed for mechanics lien release status.
Memory Technique
Coordinating Final shortcut is not a term until paper carries it.
Reference Hint
Study anchor (closed-book): memorize Mechanics lien release status from CSLB mechanics lien information; California Civil Code mechanics lien. / mechanics lien release and waiver form requirements; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?
People Also Study
Related Study Resources
Previous Question
A contract says the contractor will obtain permits, but the project manager asks the owner to handle them after signing. What should document the shift?
Next Question
A contractor wants to start demolition before the owner receives a copy of the signed contract. What is the best contract-administration practice?