A subcontractor is paid in full for final work and provides a release. Which status should the contractor avoid using before payment is actually received?
Correct Answer
D) False unconditional.
A release should not falsely state unconditional payment status before the payment condition is satisfied.
Why This Is the Correct Answer
A release should not falsely state unconditional payment status before the payment condition is satisfied.
More ca-law-business Questions
An $18,500 patio and door replacement contract is a CA home improvement job. What down payment amount is allowed at signing?
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A Class B contractor's prime contract includes fire sprinkler work classified as C-16. What must the contractor do for that scope?
A Class B contractor includes water-well drilling classified as C-57 in the overall project. What is the correct licensing path?
A registered home improvement salesperson leaves one contractor and begins selling for another. What must be checked?
A subcontractor's license classification does not cover the trade scope being subcontracted. What should the prime do before award?
A progress payment schedule asks the owner to pay for rough plumbing before that phase starts. What is the best contract-admin correction?
A contractor licensed only as Class B wants to self-perform a C-10 electrical-only service call with no other trades. What is the licensing concern?
A Class B contractor subcontracts electrical work to a properly licensed C-10 subcontractor as part of a multi-trade building project. What is the licensing result?
A material supplier on a San Jose remodel serves a preliminary notice on day 31 after first furnishing materials. Under the CA 20-day notice rule, what work period is protected by that late notice?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A contract says the contractor will obtain permits, but the project manager asks the owner to handle them after signing. What should document the shift?
Next Question
A contractor wants to start demolition before the owner receives a copy of the signed contract. What is the best contract-administration practice?