EstatePass
nascla-commercial-gcFinancial Managementmedium

A project budget shows labor costs of $85,000 and actual labor costs of $92,000. What is the labor cost variance?

Correct Answer

A) $7,000 unfavorable

Cost variance = Actual Cost - Budgeted Cost = $92,000 - $85,000 = $7,000. Since actual exceeds budget, this is unfavorable.

Answer Options
A
$7,000 unfavorable
B
$7,000 favorable
C
8.2% favorable
D
7.6% unfavorable

Why This Is the Correct Answer

Cost variance = Actual Cost - Budgeted Cost = $92,000 - $85,000 = $7,000. Since actual exceeds budget, this is unfavorable.

Was this explanation helpful?

More nascla-commercial-gc Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing