A project budget shows labor costs of $85,000 and actual labor costs of $92,000. What is the labor cost variance?
Correct Answer
A) $7,000 unfavorable
Cost variance = Actual Cost - Budgeted Cost = $92,000 - $85,000 = $7,000. Since actual exceeds budget, this is unfavorable.
Why This Is the Correct Answer
Cost variance = Actual Cost - Budgeted Cost = $92,000 - $85,000 = $7,000. Since actual exceeds budget, this is unfavorable.
More nascla-commercial-gc Questions
How long should daily reports and project correspondence typically be retained after project completion?
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
On an electrical plan, a rectangle with three parallel lines inside typically represents:
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A concrete pour requires 145 cubic yards. The concrete plant charges $135/cubic yard plus $85 delivery fee per truck. Each truck holds 8 cubic yards. What is the total concrete cost?
Next Question
A scaffold platform is 28 feet long and 7 feet wide. What is the minimum number of planks required if using 2Γ10 lumber planks that are 16 feet long?