During construction, you discover that installed work does not match the approved shop drawings. The subcontractor claims the shop drawings were wrong and wants to proceed. What should be your immediate action?
Correct Answer
B) Stop work and notify the architect/engineer for direction
When work doesn't match approved drawings, work should stop and the design team should be consulted immediately to determine the correct course of action and avoid compounding problems.
Why This Is the Correct Answer
When work doesn't match approved drawings, work should stop and the design team should be consulted immediately to determine the correct course of action and avoid compounding problems.
More nascla-commercial-gc Questions
How long should daily reports and project correspondence typically be retained after project completion?
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
On an electrical plan, a rectangle with three parallel lines inside typically represents:
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
Under the Globally Harmonized System (GHS), which hazard communication element provides detailed safety information including first aid measures and handling precautions?
Next Question
A contractor submits Application for Payment #8 requesting $485,000. The contract has 5% retainage, but the architect approves only $465,000 of the requested amount due to deficient work. How much should the owner pay?