A profitable contractor cannot meet payroll because receivables are late and suppliers require payment. What does this demonstrate?

California C-36 exam practice question · Business Finances

A profitable contractor cannot meet payroll because receivables are late and suppliers require payment. What does this demonstrate?

  • APayroll can be ignored until final payment
  • BMore revenue always solves collection timing
  • Forecast cash receipts and payments
  • DProfit guarantees cash on hand

Why C is correct

Accrual profit can exist while cash is unavailable. A cash-flow forecast identifies working-capital needs, billing timing, retainage, collections, payroll, taxes, and supplier obligations.