A contractor wants to backfill a new building drain before the required test and inspection. What is the proper sequence?

California C-36 exam practice question · Underground & Rough Systems

A contractor wants to backfill a new building drain before the required test and inspection. What is the proper sequence?

  • ASkip testing if joints look clean
  • BBackfill and rely on photographs only
  • Test before approved backfill
  • DTest only the fixtures after finishes

Why C is correct

Testing and inspection before concealment allow leaks, grade, joints, and materials to be evaluated and corrected. Photographs or a later fixture test do not provide equivalent access to buried work.