EstatePass

A home improvement contractor requests 25 percent down to buy special-order material. Is that allowed under the standard rule?

California C-20 exam practice question · Contract Requirements & Execution

A home improvement contractor requests 25 percent down to buy special-order material. Is that allowed under the standard rule?

  • AYes, special-order material is an exception
  • BYes, any amount is allowed if called a deposit
  • CNo, all down payments are prohibited
  • No; the down-payment cap applies

Why D is correct

CSLB states that the statutory cap applies without a special-order-material exception. Later payments must also be structured consistently with work and materials provided.

Practice 48 more Contract Requirements & Execution questions

Timed mock exams, a wrong book and flashcards — one subscription covers every contractor exam line.

Start studying free