A system reaches 500 microns and rises slowly to 650 after isolation, then stabilizes. What should the technician do?

California C-20 exam practice question · Fabrication, Installation & Startup

A system reaches 500 microns and rises slowly to 650 after isolation, then stabilizes. What should the technician do?

  • AOpen the system to air
  • Use the decay acceptance test
  • CIgnore isolation-valve leakage
  • DCharge solely because 500 was reached

Why B is correct

A single pump reading does not prove dehydration or tightness. Decay behavior, test time, instrument location, and manufacturer criteria determine acceptance.