Illuminated PV source circuits are routed through an accessible service area. Which installation approach recognizes their energized condition?
- Route, identify, and protect them using the applicable PV wiring rules
- BOmit disconnect labeling
- CTreat them as de-energized whenever the inverter is off for the described C-10 installation and documented operating conditions
- DSplice them loose inside a raceway
Why A is correct
The best answer is: Route, identify, and protect them using the applicable PV wiring rules. Opening an inverter or AC disconnect may not de-energize illuminated source circuits. Proper routing, identification, guarding, and approved splicing are therefore essential. This transferred field condition tests the same installation or safety principle in a different project context. The other choices conflict with the cited rule, listing, safe-work process, or necessary diagnostic sequence.