You're managing a project where steel delivery has been delayed, affecting multiple activities. Which CPM scheduling technique would best help you minimize the project delay?

Correct Answer

B) Fast tracking

Fast tracking involves performing activities in parallel that were originally planned in sequence, which can help minimize delays when materials for certain activities are delayed. This allows work to continue on non-affected activities simultaneously.

Answer Options
A
Resource leveling
B
Fast tracking
C
Crashing
D
Schedule compression

Why This Is the Correct Answer

Fast tracking is the optimal solution when specific materials are delayed because it allows you to reorganize the schedule to run activities in parallel rather than sequentially. When steel delivery is delayed, you can continue with other non-steel dependent activities simultaneously, effectively working around the delay. This technique specifically addresses material delays by maximizing the use of available resources and time on unaffected work. Fast tracking maintains project momentum without requiring additional resources or costs.

Why the Other Options Are Wrong

Option A: Resource leveling

Resource leveling focuses on smoothing out resource usage over time to avoid peaks and valleys in resource demand, but it doesn't address material delays or help minimize project duration when materials are unavailable.

Option C: Crashing

Crashing involves adding more resources (labor, equipment, or money) to accelerate activities, but this won't help when the fundamental problem is missing materials - you can't install steel that hasn't been delivered regardless of how many workers you assign.

Option D: Schedule compression

Schedule compression is a general term that encompasses both fast tracking and crashing, making it less specific than the best answer. While technically correct, fast tracking is the more precise technique for this specific scenario.

Memory Technique

FAST = Find Alternative Simultaneous Tasks - when one path is blocked by delays, create parallel paths to keep moving forward

Reference Hint

Project Management chapter, specifically CPM scheduling techniques and schedule compression methods

More Business & Finance Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing