EstatePass
Business & FinanceOperationsmedium10% of exam part

Your project schedule shows that Activity X can start as early as day 15 and must finish no later than day 28. The activity duration is 8 days. What is the total float for this activity?

Correct Answer

B) 5 days

Total float = Late Finish - Early Finish = Late Finish - (Early Start + Duration) = 28 - (15 + 8) = 28 - 23 = 5 days of float.

Answer Options
A
3 days
B
5 days
C
8 days
D
13 days

Why This Is the Correct Answer

Total float represents the amount of time an activity can be delayed without affecting the project completion date. The formula is Total Float = Late Finish - Early Finish, where Early Finish = Early Start + Duration. With an Early Start of day 15, duration of 8 days, and Late Finish of day 28, the calculation is 28 - (15 + 8) = 5 days. This means Activity X can be delayed up to 5 days without impacting the overall project schedule.

Why the Other Options Are Wrong

Option A: 3 days

This answer of 3 days likely comes from incorrectly calculating Late Start - Early Start (28-8-15 = 5, but someone might have made an arithmetic error or used wrong values).

Option C: 8 days

This answer of 8 days incorrectly uses just the activity duration, which is not what float represents. Float is about schedule flexibility, not activity length.

Option D: 13 days

This answer of 13 days incorrectly calculates Late Finish - Early Start (28 - 15 = 13), which gives the total time window available but doesn't account for the actual activity duration.

Memory Technique

Remember 'FLEF' - Float = Late Finish minus Early Finish. Think 'How much FLEX time do I have after the activity naturally ends?'

Reference Hint

Look up Critical Path Method (CPM) and float calculations in project management or scheduling chapters of your contractor reference manual.

More Business & Finance Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing