You are reviewing shop drawings for precast concrete panels. The drawings show connection details that differ from the structural drawings but appear to be structurally adequate. What should you do?
Correct Answer
D) Forward to the structural engineer for review and approval
When shop drawings show structural changes from the original design, even if they appear adequate, they must be reviewed and approved by the structural engineer of record who is qualified to evaluate the structural implications.
Why This Is the Correct Answer
When shop drawings show structural changes from the original design, even if they appear adequate, they must be reviewed and approved by the structural engineer of record who is qualified to evaluate the structural implications.
More NASCLA Questions
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
What is the minimum preheat temperature for welding ASTM A992 steel when the ambient temperature is 15Β°F?
A general contractor's balance sheet shows total assets of $850,000, current liabilities of $320,000, and long-term debt of $180,000. What is the company's equity?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A contractor's quarterly payroll totals $180,000. If the FUTA tax rate is 0.6% on the first $7,000 of each employee's wages and there are 15 employees, what is the maximum FUTA tax liability for the quarter?
Next Question
When preparing a bid for a federal project, which document typically contains the most detailed quantity information?