You are managing a commercial project and need 500 cubic yards of concrete delivered over 3 days. Your regular supplier can only provide 300 cubic yards in that timeframe. What is the most appropriate procurement strategy?
Correct Answer
B) Secure a secondary supplier for the remaining 200 cubic yards
Securing a secondary supplier ensures the project stays on schedule while meeting the full material requirement. This is a standard expediting practice that maintains quality and timeline without compromising the project scope.
Why This Is the Correct Answer
Securing a secondary supplier is the most appropriate procurement strategy because it allows the project to maintain its original schedule and scope without compromising quality. This approach demonstrates proper project management by finding a solution that meets all material requirements within the specified timeframe. Using multiple suppliers is a common and accepted practice in construction when primary suppliers cannot meet full demand, and it ensures continuity of work without delays or scope changes.
Why the Other Options Are Wrong
Option A: Delay the concrete pour by one week
Delaying the concrete pour by one week is unnecessarily disruptive and could cause cascading delays throughout the project schedule, potentially affecting other trades and increasing overall project costs.
Option C: Reduce the concrete requirement to 300 cubic yards
Reducing the concrete requirement to 300 cubic yards would compromise the project scope and structural integrity, as the 500 cubic yards was specified based on engineering requirements that cannot be arbitrarily reduced.
Option D: Use a different concrete mix that requires less volume
Using a different concrete mix that requires less volume could compromise the structural specifications and quality requirements, and may not even be feasible depending on the engineering design requirements.
Memory Technique
Remember 'SSS' - when you have a Shortage, use a Secondary Supplier to maintain Schedule
Reference Hint
Project Management and Scheduling chapter, specifically sections on material procurement and expediting practices
More Business & Finance Questions
A contractor's license expires on March 31st. If they submit a renewal application on April 15th, what additional requirement must be met under Florida regulations?
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
In Florida, what is the minimum workers' compensation insurance coverage required for construction companies with employees?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
People Also Study
Previous Question
A construction worker claims a back injury prevents them from lifting over 25 pounds. Under the ADA, which would be considered a reasonable accommodation?
Next Question
A general contractor is behind on several supplier payments due to cash flow issues. Which strategy would be most appropriate for managing accounts payable in this situation?