You are calculating the load capacity for a mobile crane lift. The crane has a 50-ton rated capacity at the planned radius. What is the maximum load you should plan to lift?
Correct Answer
C) 40 tons
Industry best practice and many safety programs require using no more than 80% of a crane's rated capacity to account for dynamic loading, wind, and other variables. 50 tons x 0.80 = 40 tons maximum planned load.
Why This Is the Correct Answer
Option C (40 tons) is correct because industry safety standards require using only 80% of a crane's rated capacity for planning purposes. This safety factor accounts for dynamic loading effects, wind conditions, rigging weight, and other variables that can affect the actual load during lifting operations. The calculation is straightforward: 50 tons × 0.80 = 40 tons maximum planned load. This practice helps prevent accidents and equipment failure by maintaining a safety buffer.
Why the Other Options Are Wrong
Option A: 50 tons
Option A uses 100% of the rated capacity, which violates safety standards and leaves no margin for dynamic forces, wind loads, or unexpected conditions that could cause the crane to exceed its safe operating limits.
Option B: 45 tons
Option B represents 90% of capacity (45 tons), which exceeds the industry-standard 80% safety factor and provides insufficient margin for safe operations.
Option D: 37.5 tons
Option D represents 75% of capacity, which is more conservative than necessary and may indicate confusion with other safety factors used in different construction applications.
Memory Technique
Remember 'EIGHTY PERCENT FOR SAFETY' - crane capacity times 0.8 keeps operations safe and prevents accidents
Reference Hint
Look up crane safety requirements in OSHA 1926 Subpart CC or the Mobile Crane Operations section of construction safety manuals
More Project Mgmt Questions
What is the minimum R-value required for wall insulation in Florida Climate Zone 2?
A subcontractor brings a new chemical product to your jobsite. Under the Globally Harmonized System (GHS), what information must be immediately available to workers?
A construction site has a trench that is 8 feet deep in Type B soil. What is the maximum allowable slope ratio for the trench walls without protective systems?
A detail drawing shows a scale of 3/4" = 1'-0". If a dimension measures 2.25 inches on the drawing, what is the actual dimension?
What is the maximum recommended spacing between drywall screws when attaching to wood studs?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Previous Question
A project requires 2,400 cubic yards of fill material to be compacted to 95% Standard Proctor density. If the borrow material has a swell factor of 25%, how many cubic yards must be excavated?
Next Question
What electrical symbol represents a duplex receptacle outlet on construction drawings?