Which of the following is typically required during contract closeout procedures?

Correct Answer

A) Submission of as-built drawings and warranties

Contract closeout procedures typically include submission of as-built drawings, warranties, operation and maintenance manuals, final lien waivers, and other project documentation required for final completion.

Answer Options
A
Submission of as-built drawings and warranties
B
Negotiation of the original contract price
C
Selection of new subcontractors
D
Initial project scheduling

Why This Is the Correct Answer

Contract closeout procedures occur at the end of a project and involve finalizing all documentation and transferring responsibility to the owner. As-built drawings show the actual construction as completed (which may differ from original plans), and warranties provide protection for the owner after project completion. These documents, along with operation manuals and lien waivers, are essential for the owner to properly maintain and operate the completed facility. This is a standard requirement in construction contracts and represents the contractor's final obligations before project completion.

Why the Other Options Are Wrong

Option B: Negotiation of the original contract price

Contract price negotiation occurs during the pre-construction phase, not during closeout. By the time closeout procedures begin, the contract price has already been established and any change orders have been processed throughout the project.

Option C: Selection of new subcontractors

Subcontractor selection happens during the pre-construction or early construction phases when planning the project team. During closeout, subcontractors are completing their final work and submitting their own closeout documentation.

Option D: Initial project scheduling

Initial project scheduling is a pre-construction activity that occurs after contract award but before construction begins. Closeout procedures happen at the end of the project when the schedule is being completed, not created.

Memory Technique

Use the acronym 'WAOL' for closeout: Warranties, As-builts, Operation manuals, Lien waivers - these are the key deliverables when you're done building.

Reference Hint

Look up contract administration and project closeout procedures in your construction management or project administration reference materials, typically found in chapters covering project phases or contract administration.

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing