Which of the following is NOT typically required for obtaining a Certificate of Occupancy?
Correct Answer
C) Contractor license verification
While the contractor must be licensed to perform the work, contractor license verification is not typically required for obtaining a Certificate of Occupancy. The CO focuses on building safety and code compliance.
Why This Is the Correct Answer
Contractor license verification is not required for obtaining a Certificate of Occupancy because the CO process focuses on the final building's compliance with safety codes and habitability standards, not on who performed the work. The licensing verification occurs during the permit application and inspection phases earlier in the construction process. By the time CO is requested, the work has already been completed and inspected, making contractor licensing a moot point for occupancy approval.
Why the Other Options Are Wrong
Option A: Final building inspection approval
Final building inspection approval is required for CO because it verifies that all construction work meets building codes and safety standards before occupancy.
Option B: Fire department approval
Fire department approval is required for CO because it ensures fire safety systems, egress routes, and fire prevention measures are properly installed and functional.
Option D: Health department approval (if applicable)
Health department approval is required for CO when applicable (restaurants, medical facilities, etc.) because it ensures compliance with health and sanitation codes.
Memory Technique
Think 'CO = Building OK' - Certificate of Occupancy checks the building's condition, not the contractor's credentials
Reference Hint
Florida Building Code Chapter 1, Section 110 - Certificate of Occupancy requirements
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
To achieve LEED Gold certification, a project must earn how many points?
Next Question
A contractor submits an Application for Payment showing 60% completion on a $2,000,000 project. With 10% retainage, what amount should the contractor receive if this is the first payment application?