Which inspection must be completed before concrete can be poured for a foundation?
Correct Answer
A) Footing inspection
The footing inspection must be completed and approved before concrete can be poured for the foundation. This ensures proper excavation, reinforcement placement, and compliance with structural requirements.
Why This Is the Correct Answer
The footing inspection is a critical checkpoint that must occur before any concrete is poured for the foundation. This inspection verifies that the excavation is to proper depth and dimensions, reinforcing steel (rebar) is correctly placed and tied, and all structural requirements are met according to the approved plans. Without this inspection approval, pouring concrete would violate building codes and could result in structural deficiencies that would be impossible to correct once the concrete is set.
Why the Other Options Are Wrong
Option B: Final inspection
Rough-in inspection occurs much later in the construction process, typically after framing is complete and before drywall installation. This inspection covers mechanical, electrical, and plumbing systems that are installed within the walls and has no relevance to foundation concrete pouring.
Option C: Framing inspection
Framing inspection occurs after the foundation is complete and the structural framing is installed. This inspection verifies lumber sizes, connections, and structural elements of the frame, but it cannot occur until after the foundation concrete has been poured, cured, and is ready to support the structure.
Memory Technique
Think 'BEFORE the POUR' - Footings must be inspected BEFORE you POUR concrete. Also remember: 'Feet first' - footings (like feet) come before everything else in construction.
Reference Hint
Florida Building Code - Building, Chapter 18 (Soils and Foundations) and local building inspection requirements
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
Quality control testing reveals that 5% of concrete cylinders from a pour failed strength tests. According to ACI standards, what action is typically required?
Next Question
A contractor is building a shopping center that requires 150 parking spaces. If the zoning ordinance requires 1 parking space per 250 square feet of retail space, what is the maximum allowable retail square footage?
