Which estimating method provides the highest level of accuracy for construction cost estimates?
Correct Answer
C) Detailed unit cost method
The detailed unit cost method provides the highest accuracy because it breaks down all work into individual components with specific quantities, labor hours, and material costs.
Why This Is the Correct Answer
The detailed unit cost method provides the highest accuracy because it breaks down every aspect of construction into individual work items with specific quantities, labor hours, material costs, and equipment needs. This granular approach accounts for all project variables and allows for precise cost calculations based on actual field conditions. It requires the most time and effort but delivers estimates with accuracy levels of ±5-10%, making it ideal for final bidding and project execution.
Why the Other Options Are Wrong
Option A: Square foot method
The square foot method is a conceptual estimating technique that uses cost per square foot multipliers based on building type and provides only rough order-of-magnitude estimates with accuracy of ±25-50%, making it suitable for early planning but not detailed bidding.
Option B: Assemblies method
The assemblies method (also called systems method) groups related components together but still lacks the granular detail of individual unit costs, providing moderate accuracy of ±15-25% which is better than square foot but less precise than detailed unit costing.
Option D: Parametric method
The parametric method uses mathematical models and statistical relationships between cost and project variables, but relies on historical data that may not account for specific project conditions, resulting in lower accuracy than detailed unit cost analysis.
Memory Technique
Think 'DETAIL = ACCURATE' - the more detailed the breakdown (individual units), the more accurate the estimate becomes.
Reference Hint
Florida Building Construction Standards and Practices - Chapter on Cost Estimating Methods and Project Management sections
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
As-built drawings are typically required to be submitted:
Next Question
In a Guaranteed Maximum Price (GMP) contract, if the actual project costs are $485,000 and the GMP is $500,000 with a 50/50 cost savings split, what is the contractor's total compensation if the base fee is $35,000?