EstatePass
Contract AdminContractsmedium40% of exam part

Which document would typically contain the specific scope of work, schedule, and payment terms between a general contractor and subcontractor?

Correct Answer

C) AIA A401

AIA A401 is the Standard Form of Agreement Between Contractor and Subcontractor, which contains the specific scope, schedule, payment terms, and other provisions governing the subcontract relationship.

Answer Options
A
AIA A101
B
AIA A201
C
AIA A401
D
Notice to Proceed

Why This Is the Correct Answer

AIA A401 is specifically designed as the Standard Form of Agreement Between Contractor and Subcontractor. This document establishes the contractual relationship between the general contractor and subcontractor, detailing the subcontractor's scope of work, project schedule requirements, payment terms, and performance obligations. It serves as the primary governing document for subcontract work and includes provisions for coordination with the prime contract.

Why the Other Options Are Wrong

Option A: AIA A101

AIA A101 is the Standard Form of Agreement Between Owner and Contractor, which governs the relationship between the project owner and general contractor, not between contractor and subcontractor.

Option B: AIA A201

AIA A201 is the General Conditions of the Contract for Construction, which provides standard terms and conditions but is not the agreement document itself that contains specific scope, schedule, and payment terms.

Option D: Notice to Proceed

Notice to Proceed is a formal notification document that authorizes the start of work but does not contain detailed scope, schedule, or payment terms - these are established in the contract agreement.

Memory Technique

Think 'A401 = Agreement FOR ONE subcontractor' - the '4' represents the fourth party relationship (after owner, architect, contractor comes subcontractor)

Reference Hint

Florida Building Code Chapter 1, Section 107 - Construction Documents and AIA Contract Documents reference guide

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing