EstatePass
Contract AdminPermitseasy20% of exam part

Which document must be prominently displayed at the job site throughout the construction period?

Correct Answer

B) Building permit

Building permits must be prominently displayed at the construction site and remain posted throughout the duration of the project until completion.

Answer Options
A
Contractor's license
B
Building permit
C
Zoning approval
D
Certificate of Occupancy

Why This Is the Correct Answer

Building permits must be prominently displayed at the construction site throughout the entire construction period as required by Florida building codes and local ordinances. This ensures that inspectors, officials, and other stakeholders can easily verify that proper permits have been obtained for the work being performed. The permit contains important information about the approved scope of work, approved plans, and contact information for the project.

Why the Other Options Are Wrong

Option A: Contractor's license

Zoning approval is obtained before construction begins and is part of the preliminary approval process. While important for project compliance, it's not required to be prominently displayed at the construction site during the building phase.

Option C: Zoning approval

While contractors must maintain valid licenses, the contractor's license is not required to be prominently displayed at the job site. The license information is typically provided during the permitting process and kept in company records.

Memory Technique

Remember 'BUILD with PERMIT on display' - the Building permit must be visible while you BUILD, just like a parking permit must be displayed in your car window.

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.