Which document is required before utilities can be permanently connected to a new commercial building?
Correct Answer
A) Certificate of Occupancy
A Certificate of Occupancy is required before permanent utility connections can be made to a new commercial building. This ensures the building meets all safety and code requirements for occupancy.
Why This Is the Correct Answer
A Certificate of Occupancy (CO) is the final document that certifies a building is safe and compliant with all applicable codes for occupancy. Utility companies require this certificate before making permanent connections because it confirms the building has passed all inspections, meets safety standards, and is legally authorized for occupancy. The CO represents the completion of the entire construction and inspection process, ensuring utilities can be safely and legally connected.
Why the Other Options Are Wrong
Option B: Temporary Certificate of Occupancy
A Temporary Certificate of Occupancy allows limited occupancy for a specific period while minor items are completed. However, utilities typically require the final, permanent Certificate of Occupancy before making permanent connections to ensure all work is fully completed and approved.
Option C: Final inspection approval
Final inspection approval is just one step in the process leading to the Certificate of Occupancy. While inspections must pass, the formal CO document is what utility companies specifically require as proof that the building is legally ready for permanent service connections.
Option D: Building permit
A building permit only authorizes construction to begin and allows temporary utility connections during construction. It does not certify that the building is complete, safe, or ready for occupancy, which is required before permanent utility connections can be established.
Memory Technique
Remember 'CO = Connected and Occupied' - Certificate of Occupancy allows both permanent utility connections and building occupancy together.
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
