Which cost estimating method is most appropriate for preliminary budget development during the design phase?
Correct Answer
D) Square foot method
The square foot method is ideal for preliminary budgets when detailed plans aren't available, using cost per square foot based on building type and quality level.
Why This Is the Correct Answer
The square foot method is most appropriate for preliminary budget development because it provides quick, reasonably accurate cost estimates when only basic building information is available during early design phases. This method uses historical cost data per square foot for similar building types and quality levels, making it ideal when detailed plans, specifications, and material takeoffs are not yet complete. It strikes the right balance between speed and accuracy needed for initial budgeting decisions.
Why the Other Options Are Wrong
Option B: Assemblies method
The detailed unit cost method requires complete plans, specifications, and detailed material takeoffs to calculate costs for individual components, making it too time-consuming and impractical for preliminary budgets when such detailed information isn't available yet.
Option C: Historical cost database method
The assemblies method requires more detailed design information than typically available during preliminary phases, as it estimates costs for building systems and assemblies that need to be defined and specified first.
Memory Technique
Think 'Square foot = Quick start' - when you only know the building's footprint and basic type, use square foot method for fast preliminary estimates.
Reference Hint
Look up cost estimating methods in the project management or construction estimating chapter of your reference materials
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
