EstatePass
Contract AdminPreconstructionmedium27% of exam part

When using the square foot estimating method, which factor has the GREATEST impact on cost per square foot accuracy?

Correct Answer

B) Similarity of building type and quality to the database source

The accuracy of square foot estimating depends most heavily on using data from similar building types and quality levels. Comparing a warehouse to an office building would yield very inaccurate results.

Answer Options
A
Geographic location adjustments
B
Similarity of building type and quality to the database source
C
Current material price fluctuations
D
Building height and configuration

Why This Is the Correct Answer

Square foot estimating accuracy depends fundamentally on comparing like-to-like projects. The database source must contain buildings of similar type, quality, complexity, and construction methods. A luxury office building has vastly different cost drivers than a basic warehouse - different materials, finishes, systems, and labor requirements. Without comparable building types and quality levels in the database, the cost per square foot becomes meaningless and can lead to estimates that are off by 50% or more.

Why the Other Options Are Wrong

Option A: Geographic location adjustments

While geographic location adjustments are important for final pricing accuracy, they are mathematical multipliers applied to the base cost. If the underlying square foot data comes from dissimilar building types, even perfect location adjustments cannot correct the fundamental mismatch in construction complexity and quality.

Option C: Current material price fluctuations

Material price fluctuations affect current market conditions but can be adjusted through escalation factors or current pricing updates. However, if the base square foot data comes from incompatible building types, no amount of material price adjustment can correct the fundamental difference in construction scope and quality.

Memory Technique

Remember 'Apples to Apples' - you can't estimate an apple orchard using orange grove data. Square foot estimating requires matching building types like matching fruit types.

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.