EstatePass
Contract AdminPreconstructionhard27% of exam part

When using the assemblies method for cost estimating, which level of project development is most appropriate?

Correct Answer

C) Design development phase

The assemblies method is most effective during design development when building systems are defined but detailed specifications may not be complete. It provides more accuracy than square foot pricing while requiring less detail than unit cost estimates.

Answer Options
A
Conceptual design phase
B
Schematic design phase
C
Design development phase
D
Construction documents phase

Why This Is the Correct Answer

CORRECT_ANSWER - The assemblies method is most appropriate during the design development phase because this is when building systems and major components are clearly defined, but detailed specifications and drawings are not yet complete. This method allows for reasonably accurate cost estimates based on building assemblies (like wall systems, roofing systems, etc.) without requiring the detailed unit pricing that comes later. It bridges the gap between early conceptual estimates and detailed unit cost estimates.

Why the Other Options Are Wrong

Option A: Conceptual design phase

The conceptual design phase is too early for assemblies method because building systems and components are not yet defined in sufficient detail. At this stage, square footage or cubic footage methods are more appropriate.

Option B: Schematic design phase

The schematic design phase typically still lacks the detail needed for assemblies method. While basic building layouts are established, the specific systems and assemblies are not sufficiently defined for this estimating approach.

Option D: Construction documents phase

The construction documents phase provides too much detail for assemblies method - at this stage, detailed unit cost estimates are more appropriate and accurate since all specifications, materials, and methods are fully defined.

Memory Technique

Think 'DD = Defined Systems' - Design Development is when systems are Defined, making it perfect for assemblies (system-based) estimating.

Reference Hint

Look for cost estimating methods in the project management or construction administration sections, typically covering the relationship between design phases and appropriate estimating techniques.

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing