When should as-built drawings be updated during the construction process?
Correct Answer
C) Continuously as changes occur during construction
As-built drawings should be updated continuously as changes occur during construction to ensure accuracy and prevent information from being lost. Waiting until the end of the project often results in incomplete or inaccurate documentation.
Why This Is the Correct Answer
As-built drawings must be updated continuously as changes occur during construction to maintain accuracy and completeness. Construction projects frequently involve field changes, design modifications, and unforeseen conditions that deviate from original plans. If updates are delayed, critical information about actual installation locations, dimensions, and modifications can be forgotten or lost. Continuous updating ensures that the final as-built drawings accurately reflect the actual constructed conditions.
Why the Other Options Are Wrong
Option A: Only at project completion
Waiting until project completion to update as-built drawings often results in incomplete or inaccurate documentation because workers may forget specific changes, field modifications, or exact locations of installed systems that occurred months earlier.
Option B: Monthly during progress meetings
Monthly updates during progress meetings are too infrequent and may miss important changes that occur between meetings, leading to gaps in documentation and potential loss of critical construction details.
Option D: After each major construction phase is completed
Updating only after major phases are completed creates gaps in documentation and increases the risk of forgetting smaller but important changes that occur during each phase, potentially resulting in inaccurate final drawings.
Memory Technique
Think 'AS changes happen, AS-BUILT drawings get updated' - the word 'AS' appears in both the timing and the document type to remember continuous updating.
Reference Hint
Florida Building Code Chapter 1, Administrative provisions regarding construction documents and record drawings
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass