When should as-built drawings be updated during construction?
Correct Answer
B) Continuously as changes occur during construction
As-built drawings should be updated continuously as changes occur to ensure accuracy and completeness. Waiting until project completion may result in forgotten details or inaccurate documentation.
Why This Is the Correct Answer
As-built drawings must be updated continuously throughout construction to maintain accuracy and completeness. Construction projects involve numerous field changes, modifications, and unforeseen conditions that deviate from original plans. If updates are delayed, critical details may be forgotten or incorrectly documented, leading to inaccurate record drawings. Continuous updating ensures that all changes are captured in real-time while the information is fresh and accurate.
Why the Other Options Are Wrong
Option A: Only at project completion
Waiting until project completion to update as-built drawings is problematic because many construction details and changes will be forgotten by that time, leading to incomplete or inaccurate documentation that fails to reflect actual field conditions.
Option C: Monthly during progress meetings
Monthly updates during progress meetings are insufficient because construction changes occur daily, and waiting a month between updates means many critical details and modifications could be forgotten or incorrectly documented.
Option D: Only when requested by the owner
Relying solely on owner requests for as-built updates is inadequate because the owner may not be aware of all field changes, and the contractor has a professional responsibility to maintain accurate construction documentation regardless of specific requests.
Memory Technique
Think 'ABC' - As-Built drawings need Continuous updates, not 'ABE' - As-Built at End
Reference Hint
Florida Building Code, Chapter 1, Section 107 - Submittal Documents, or AIA Document A201 - General Conditions, Article 3.11 - Record Documents
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
In a unit price contract for 5,000 linear feet of fencing at $45 per linear foot, the actual quantity installed was 5,250 linear feet. What is the total contract amount?
Next Question
During bid evaluation, a contractor receives the following electrical subcontractor bids: $85,000, $92,000, $78,000, and $105,000. Which bid requires the most careful scrutiny?