When should as-built drawings be updated during construction?

Correct Answer

B) Continuously as changes occur

As-built drawings should be updated continuously as changes occur during construction to maintain accurate records. This ensures all modifications are properly documented and prevents information from being lost or forgotten.

Answer Options
A
Only at project completion
B
Continuously as changes occur
C
Monthly during progress meetings
D
When requested by the owner

Why This Is the Correct Answer

As-built drawings must be updated continuously as changes occur to maintain accurate documentation throughout the construction process. Waiting until later stages means critical details about modifications, field changes, and design adjustments could be forgotten or lost. Real-time updates ensure that all stakeholders have access to current information and that the final as-built drawings accurately reflect the completed project. This practice is essential for future maintenance, renovations, and compliance with building codes.

Why the Other Options Are Wrong

Option A: Only at project completion

Waiting until project completion to update as-built drawings is problematic because many construction details and change reasons will be forgotten by then, leading to incomplete or inaccurate documentation.

Option C: Monthly during progress meetings

Monthly updates during progress meetings are insufficient because many changes occur between meetings, and waiting a month to document modifications risks losing important details about the work performed.

Option D: When requested by the owner

Updating as-built drawings only when requested by the owner is inadequate because it makes the process reactive rather than proactive, potentially missing critical changes that occur when the owner isn't actively monitoring.

Memory Technique

Think 'ABC' - As-Built drawings need Continuous updates, not 'ABD' - As-Built at the enD

Reference Hint

Florida Building Code Chapter 1 - Administration and Enforcement, or AIA Contract Documents regarding record drawings and documentation requirements

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing