EstatePass
Contract AdminPreconstructioneasy27% of exam part

When performing a quantity takeoff for drywall, which measurement should be deducted from the gross wall area?

Correct Answer

A) All door and window openings

Standard practice in drywall quantity takeoffs is to deduct all door and window openings from the gross wall area to determine the net area requiring drywall installation.

Answer Options
A
All door and window openings
B
Only window openings
C
Door and window openings greater than 100 square feet
D
Only door openings

Why This Is the Correct Answer

In drywall quantity takeoffs, all door and window openings must be deducted from the gross wall area because these areas do not require drywall installation. This is standard industry practice regardless of the size of the opening. The goal is to calculate the actual net area where drywall will be installed, which means subtracting every opening where drywall won't be needed.

Why the Other Options Are Wrong

Option B: Only window openings

This is incorrect because there is no industry standard threshold of 100 square feet for deducting openings. All openings, regardless of size, should be deducted since no drywall is installed in these areas.

Option C: Door and window openings greater than 100 square feet

This is incomplete because it only accounts for window openings while ignoring door openings, which also don't require drywall and should be deducted.

Memory Technique

Think 'NO DRYWALL = NO PAY' - anywhere you don't install drywall (doors/windows), you don't get paid for material, so deduct ALL openings from your estimate.

Reference Hint

Look up 'Quantity Takeoffs' or 'Drywall Estimating' in construction estimating references or the Building Construction section of exam materials.

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.