When performing a quantity takeoff for drywall, which measurement should be deducted from the gross wall area?
Correct Answer
A) All door and window openings
Standard practice in drywall quantity takeoffs is to deduct all door and window openings from the gross wall area to determine the net area requiring drywall installation.
Why This Is the Correct Answer
In drywall quantity takeoffs, all door and window openings must be deducted from the gross wall area because these areas do not require drywall installation. This is standard industry practice regardless of the size of the opening. The goal is to calculate the actual net area where drywall will be installed, which means subtracting every opening where drywall won't be needed.
Why the Other Options Are Wrong
Option B: Only window openings
This is incorrect because there is no industry standard threshold of 100 square feet for deducting openings. All openings, regardless of size, should be deducted since no drywall is installed in these areas.
Option C: Door and window openings greater than 100 square feet
This is incomplete because it only accounts for window openings while ignoring door openings, which also don't require drywall and should be deducted.
Memory Technique
Think 'NO DRYWALL = NO PAY' - anywhere you don't install drywall (doors/windows), you don't get paid for material, so deduct ALL openings from your estimate.
Reference Hint
Look up 'Quantity Takeoffs' or 'Drywall Estimating' in construction estimating references or the Building Construction section of exam materials.
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
