When performing a quantity takeoff for drywall, which measurement should be deducted from the gross wall area?
Correct Answer
D) All door and window openings
Standard practice in drywall quantity takeoffs is to deduct all door and window openings from the gross wall area to determine the net area requiring drywall installation.
Why This Is the Correct Answer
In drywall quantity takeoffs, all door and window openings must be deducted from the gross wall area because these areas do not require drywall installation. This is standard industry practice regardless of the size of the opening. The goal is to calculate the actual net area where drywall will be installed, which means subtracting every opening where drywall won't be needed.
Why the Other Options Are Wrong
Option A: Only door openings
This is incomplete because it only accounts for door openings while ignoring window openings, which also don't require drywall and should be deducted.
Option B: Only window openings
This is incomplete because it only accounts for window openings while ignoring door openings, which also don't require drywall and should be deducted.
Option C: Door and window openings greater than 100 square feet
This is incorrect because there is no industry standard threshold of 100 square feet for deducting openings. All openings, regardless of size, should be deducted since no drywall is installed in these areas.
Memory Technique
Think 'NO DRYWALL = NO PAY' - anywhere you don't install drywall (doors/windows), you don't get paid for material, so deduct ALL openings from your estimate.
Reference Hint
Look up 'Quantity Takeoffs' or 'Drywall Estimating' in construction estimating references or the Building Construction section of exam materials.
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass