EstatePass
Contract AdminPreconstructionhard27% of exam part

When estimating concrete work, a contractor calculates 150 cubic yards are needed. Applying a 10% waste factor and 5% overage allowance, what quantity should be ordered?

Correct Answer

C) 173 cubic yards

Calculate: 150 cubic yards × 1.10 (waste factor) × 1.05 (overage allowance) = 150 × 1.155 = 173.25, rounded to 173 cubic yards.

Answer Options
A
165 cubic yards
B
172.5 cubic yards
C
173 cubic yards
D
180 cubic yards

Why This Is the Correct Answer

Option C correctly applies both the 10% waste factor and 5% overage allowance as multiplicative factors. The calculation is: 150 cubic yards × 1.10 (waste factor) × 1.05 (overage allowance) = 150 × 1.155 = 173.25 cubic yards. Since concrete is typically ordered in whole cubic yards, this rounds to 173 cubic yards, ensuring adequate material for the project.

Why the Other Options Are Wrong

Option A: 165 cubic yards

Option D of 180 cubic yards significantly overestimates the required concrete. This might result from incorrectly calculating 150 × 1.20 (adding 20% total) or applying the factors incorrectly. While having extra material seems safer, over-ordering increases project costs unnecessarily and violates proper estimating practices.

Option B: 172.5 cubic yards

Option B represents the intermediate calculation of 150 × 1.15 = 172.5 cubic yards, which incorrectly adds the waste factor and overage allowance as percentages rather than applying them as separate multiplicative factors. This additive approach underestimates the total concrete needed.

Option D: 180 cubic yards

Option A incorrectly adds the percentages (10% + 5% = 15%) instead of multiplying the factors. This gives 150 × 1.15 = 172.5, then rounds down to 165, which significantly underestimates the required concrete quantity and could lead to material shortages on the job site.

Memory Technique

Remember 'Multiply, Don't Add' - waste and overage factors are multiplicative: 1.10 × 1.05 = 1.155. Think 'WOM' - Waste times Overage times Material.

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.