EstatePass
Project MgmtConstructionmedium63% of exam part

When can concrete forms typically be stripped from a suspended slab in normal weather conditions?

Correct Answer

D) 14 days

Forms supporting suspended slabs should remain in place for 14 days under normal conditions to ensure the concrete has gained sufficient strength (typically 70% of design strength) to support its own weight and construction loads.

Answer Options
A
24 hours
B
3 days
C
7 days
D
14 days

Why This Is the Correct Answer

Suspended slabs require 14 days of curing time before form removal because they must support their own weight plus construction loads without intermediate support. During this period, concrete typically reaches 70% of its design strength, which is the minimum required for safe form removal. Unlike slabs on grade that are supported by the ground, suspended slabs rely entirely on their structural integrity once forms are removed.

Why the Other Options Are Wrong

Option A: 24 hours

24 hours is far too early for suspended slab form removal - concrete has only gained about 20-30% of its design strength at this point, which is insufficient to support the slab's own weight safely.

Option B: 3 days

3 days allows concrete to reach only about 50% of design strength, which is adequate for vertical elements like walls but insufficient for suspended structural elements that must carry loads.

Option C: 7 days

7 days typically allows concrete to reach about 65% of design strength, which is close but still below the 70% minimum required for safe removal of suspended slab forms.

Memory Technique

Think 'Suspended = Serious waiting' - suspended slabs are serious structural elements that need the full 14 days, or remember '2 weeks for slabs that don't touch the ground.'

Reference Hint

ACI 318 Building Code Requirements for Structural Concrete, Chapter 6 - Formwork and Shoring, or Florida Building Code Chapter 19 - Concrete

More Project Mgmt Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing