What is the primary purpose of including allowances in a construction estimate?
Correct Answer
B) To account for items not yet specified
Allowances are budget placeholders for items that are known to be required but have not yet been fully specified or selected, such as fixtures, finishes, or equipment.
Why This Is the Correct Answer
Allowances are budget placeholders included in construction estimates for items that are known to be required but have not yet been fully specified, detailed, or selected. These typically include fixtures, finishes, appliances, or equipment where the exact type, brand, or model hasn't been determined during the estimating phase. Allowances ensure the budget accounts for these necessary items while providing flexibility for final selection during construction, preventing cost overruns when specifications are finalized.
Why the Other Options Are Wrong
Option C: To cover general conditions costs
Contractor profit is a separate line item in construction estimates, typically calculated as a percentage of project costs. Profit margins are explicitly identified and not hidden within allowances, which serve a different budgeting purpose.
Option D: To cover contractor profit
Change orders address modifications to the original scope of work after contract execution. Allowances are predetermined budget amounts for known but unspecified items, not contingency funds for scope changes or unforeseen work.
Memory Technique
Remember 'Allowances Allow for the Unknown' - they're budget placeholders for items you know you need but haven't specified yet, like saying 'we'll need light fixtures but haven't picked them out.'
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
