What is the primary purpose of as-built drawings?
Correct Answer
B) To document actual construction conditions and changes made during construction
As-built drawings document the actual construction as it was built, including any field changes, modifications, or deviations from the original design drawings.
Why This Is the Correct Answer
As-built drawings serve as the final record of how a project was actually constructed, capturing all field changes, modifications, and deviations from the original plans. They are created during and after construction to document the true conditions of installed systems, structural elements, and utilities. These drawings are essential for future maintenance, renovations, and facility management. They provide an accurate representation of what was actually built rather than what was originally designed.
Why the Other Options Are Wrong
Option A: To show the original design intent
Original design intent is shown in the initial construction drawings and specifications, not as-built drawings. As-built drawings specifically document deviations FROM the original design.
Option C: To provide shop drawing details
Shop drawings are detailed drawings prepared by subcontractors showing how specific components will be fabricated and installed. As-built drawings document the final constructed conditions, not fabrication details.
Option D: To show future renovation possibilities
Future renovation possibilities are shown in conceptual or planning drawings. As-built drawings document existing conditions, not future potential changes.
Memory Technique
Think 'AS-BUILT = ACTUAL BUILT' - both start with 'A' and emphasize documenting reality, not plans or possibilities
Reference Hint
Florida Building Code Chapter 1 - Administration and Enforcement, or AIA Contract Documents regarding record drawings and project closeout requirements
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
A quality control checklist for concrete placement should include verification of all the following EXCEPT:
Next Question
You receive three electrical subcontractor bids: Contractor A - $45,000 (excludes permits), Contractor B - $48,500 (includes all items), Contractor C - $44,200 (excludes temporary power). The permit cost is $800 and temporary power is $1,200. Which bid should be selected based on total cost?