EstatePass
Contract AdminContractseasy40% of exam part

What is the primary difference between a unit price contract and a lump sum contract?

Correct Answer

B) Unit price contracts pay based on actual quantities installed, lump sum contracts pay a fixed amount

Unit price contracts pay based on actual quantities of work performed at predetermined unit rates, while lump sum contracts pay a fixed total amount regardless of actual quantities.

Answer Options
A
Unit price contracts include material costs, lump sum contracts do not
B
Unit price contracts pay based on actual quantities installed, lump sum contracts pay a fixed amount
C
Unit price contracts require performance bonds, lump sum contracts do not
D
Unit price contracts have shorter payment terms than lump sum contracts

Why This Is the Correct Answer

Option B correctly identifies the fundamental difference between these contract types. Unit price contracts establish predetermined rates for specific units of work (per square foot, per cubic yard, etc.) and payment is calculated by multiplying these rates by the actual quantities installed. Lump sum contracts establish a fixed total price for the entire project scope, regardless of the actual quantities of materials or labor required. This distinction is crucial for contractors to understand risk allocation and payment structures.

Why the Other Options Are Wrong

Option A: Unit price contracts include material costs, lump sum contracts do not

Both unit price and lump sum contracts typically include material costs in their pricing structure. The inclusion or exclusion of material costs is not what differentiates these contract types - it's how the total payment is calculated and structured.

Option C: Unit price contracts require performance bonds, lump sum contracts do not

Performance bond requirements are determined by project specifications, contract value, and owner requirements, not by the contract pricing method. Both unit price and lump sum contracts may or may not require performance bonds depending on these factors.

Option D: Unit price contracts have shorter payment terms than lump sum contracts

Payment terms (such as monthly progress payments, net 30 days, etc.) are negotiated contract provisions that are independent of whether the contract uses unit pricing or lump sum pricing. Both contract types can have identical payment schedules.

Memory Technique

Think 'Unit = Actual' (you get paid for actual units installed) vs 'Lump = Locked' (payment amount is locked in regardless of quantities)

Reference Hint

Construction Contracting chapter on Contract Types and Pricing Methods

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing