EstatePass
Contract AdminPreconstructionmedium27% of exam part

What is the most appropriate contingency percentage for a renovation project in an existing building where unknown conditions are likely?

Correct Answer

A) 10-15%

Renovation projects typically require higher contingencies (10-15%) due to unknown conditions like hidden structural issues, outdated systems, and unforeseen complications that are common in existing buildings.

Answer Options
A
10-15%
B
5-8%
C
3-5%
D
20-25%

Why This Is the Correct Answer

Renovation projects in existing buildings require 10-15% contingency because they involve significant unknowns that cannot be fully assessed until work begins. Hidden structural damage, outdated electrical/plumbing systems, asbestos, lead paint, and code compliance issues are common discoveries that can substantially increase project costs. This higher contingency percentage accounts for the inherent risks and uncertainties present in older buildings that new construction projects don't face.

Why the Other Options Are Wrong

Option C: 3-5%

20-25% contingency is excessively high and would make most renovation projects financially unfeasible, though it might be considered for extremely complex historic renovations or disaster recovery projects.

Option D: 20-25%

5-8% contingency is still insufficient for renovation projects, as this range is better suited for minor remodeling or projects with minimal structural involvement.

Memory Technique

Use 'RENO = 10+' - RENoVation projects need 10% or more contingency due to the unknown conditions lurking behind walls and under floors.

Reference Hint

Florida Building Code Chapter 1 - General Provisions, and construction estimating references covering contingency planning for renovation work

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.