What is the minimum bond amount required for a Certified General Contractor license in Florida?
Correct Answer
B) $50,000
Florida requires a minimum surety bond of $50,000 for Certified General Contractor licenses. This bond protects consumers against financial loss due to contractor default or improper work performance.
Why This Is the Correct Answer
Florida Statute 489.115 specifically mandates that Certified General Contractors must maintain a minimum surety bond of $50,000. This bond amount is set by the Florida Construction Industry Licensing Board and serves as financial protection for consumers against contractor defaults, abandonment of projects, or failure to pay subcontractors and suppliers. The $50,000 minimum applies regardless of the contractor's project size or annual revenue, though contractors may choose to carry higher bond amounts for larger projects or business purposes.
Why the Other Options Are Wrong
Option A: $25,000
$25,000 is below the statutory minimum requirement and would not meet Florida's licensing standards for general contractors.
Option C: $75,000
$75,000 exceeds the minimum requirement, though contractors may voluntarily carry this amount or higher for business reasons.
Option D: $100,000
$100,000 is double the minimum requirement and while acceptable, it's not the minimum amount mandated by Florida law.
Memory Technique
Think 'Fifty for Florida General' - the $50K bond is the foundation amount that all Florida general contractors must have as their minimum financial protection.
Reference Hint
Florida Statute 489.115 - Licensure requirements; Florida Administrative Code 61G4-15 - Financial responsibility requirements
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
An owner requests a change that will add $35,000 to the contract price and 12 days to the schedule. The contractor's markup on changes is 15% for overhead and profit. What should be the total change order amount?
Next Question
Under Florida lien law, what is the time limit for filing a Claim of Lien after the contractor's final furnishing of labor or materials?