What is the maximum monetary limit for a Registered General Contractor in Florida?
Correct Answer
A) $200,000 per contract and $600,000 aggregate
Florida Statute Chapter 489 establishes that Registered General Contractors are limited to $200,000 per individual contract with an aggregate limit of $600,000 for all outstanding contracts at any given time.
Why This Is the Correct Answer
Florida Statute Chapter 489 specifically establishes monetary limitations for Registered General Contractors at $200,000 per individual contract with an aggregate limit of $600,000 for all outstanding contracts. This is a fundamental licensing requirement that distinguishes Registered General Contractors from Certified General Contractors. The aggregate limit means the total value of all active contracts cannot exceed $600,000 at any given time. These limits are designed to ensure contractors work within their experience and financial capacity levels.
Why the Other Options Are Wrong
Option B: $300,000 per contract and $900,000 aggregate
This option shows incorrect monetary limits that are too high for Registered General Contractors. The $300,000/$900,000 limits do not exist in Florida Statute Chapter 489 and would exceed the statutory restrictions placed on this license classification.
Option C: $500,000 per contract and $1,500,000 aggregate
These monetary limits are significantly higher than what Florida law permits for Registered General Contractors. The $500,000/$1,500,000 amounts would be more appropriate for higher-level contractor classifications and exceed the statutory caps established in Chapter 489.
Option D: No monetary limitation
This is incorrect because Florida Statute Chapter 489 clearly establishes specific monetary limitations for Registered General Contractors. Having no monetary limitation would apply to Certified General Contractors, not Registered General Contractors, which are specifically created as a limited license category.
Memory Technique
Think '2-6 Rule': $200K per contract, $600K aggregate. The aggregate is always 3 times the individual contract limit (200 × 3 = 600).
Reference Hint
Florida Statute Chapter 489 - Construction Industry Licensing, specifically the sections defining Registered General Contractor limitations
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?