What information is typically NOT included in as-built drawings?
Correct Answer
C) Material costs and labor hours
As-built drawings document the physical aspects of the completed construction, including actual locations, dimensions, and changes. Material costs and labor hours are financial information typically found in project cost records, not as-built drawings.
Why This Is the Correct Answer
As-built drawings are technical documentation that record the physical reality of completed construction. They focus exclusively on spatial and structural information - showing what was actually built, where it was placed, and how it differs from original plans. Material costs and labor hours are financial data that belong in project accounting records, cost reports, and billing documentation, not in technical drawings that document physical construction elements.
Why the Other Options Are Wrong
Option A: Changes made during construction
Changes made during construction are a primary component of as-built drawings. These drawings specifically document deviations from original plans, including field modifications, design changes, and construction adjustments that occurred during the building process.
Option B: Final locations of utilities and structural elements
Final locations of utilities and structural elements are fundamental information in as-built drawings. These drawings must accurately show where pipes, conduits, beams, and other building systems were actually installed for future reference and maintenance.
Option D: Actual dimensions of installed components
Actual dimensions of installed components are essential information in as-built drawings. These drawings record the true measurements of what was built, which may differ from original design dimensions due to field conditions or modifications.
Memory Technique
Remember 'As-Built = As-BUILT' - they show what was physically BUILT, not what was BILLED. Financial information goes in billing records, not building drawings.
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?