Under Florida Statute Chapter 713, what is the maximum time limit for filing a Claim of Lien after recording the Notice of Nonpayment?
Correct Answer
B) 90 days
Florida Statute 713.08 requires that a Claim of Lien be filed within 90 days after recording the Notice of Nonpayment. This is a critical deadline that cannot be extended.
Why This Is the Correct Answer
Florida Statute 713.08 specifically establishes a 90-day time limit for filing a Claim of Lien after recording the Notice of Nonpayment. This deadline is absolute and cannot be waived or extended by any party or court. The 90-day period begins running from the date the Notice of Nonpayment is recorded in the public records. Missing this deadline results in the complete loss of lien rights, making it one of the most critical deadlines in Florida construction law.
Why the Other Options Are Wrong
Option A: 45 days
45 days is too short and does not align with Florida Statute 713.08. This timeframe might be confused with other construction-related deadlines but is not the correct period for filing a Claim of Lien after Notice of Nonpayment.
Option C: 120 days
120 days exceeds the statutory requirement under Florida Statute 713.08. While this might seem like a reasonable timeframe, Florida law specifically requires action within 90 days, not 120 days.
Option D: 180 days
180 days is far too long and does not comply with Florida Statute 713.08. This extended timeframe would undermine the purpose of lien law, which requires prompt action to preserve rights and provide notice to property owners.
Memory Technique
Think '90 days to save your lien' - the Notice of Nonpayment gives you exactly 90 days to file your Claim of Lien or lose your rights forever.
Reference Hint
Florida Statutes Chapter 713 - Construction Liens, specifically Section 713.08
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass