EstatePass
Contract AdminContractseasy40% of exam part

Under Florida Statute Chapter 713, what is the maximum time limit for a general contractor to record a Claim of Lien after the last day of work or furnishing of materials?

Correct Answer

B) 90 days

Florida Statute 713.08 requires that a Claim of Lien must be recorded within 90 days after the last day the lienor performed labor or furnished materials. This is a critical deadline that cannot be extended.

Answer Options
A
60 days
B
90 days
C
120 days
D
180 days

Why This Is the Correct Answer

Florida Statute 713.08 specifically establishes a 90-day deadline for recording a Claim of Lien after the last day of work or furnishing materials. This statutory requirement is absolute and cannot be waived or extended by agreement between parties. The 90-day period begins running from the actual last day the contractor performed work or delivered materials to the project site. Missing this deadline results in the complete loss of lien rights, making it one of the most critical deadlines in Florida construction law.

Why the Other Options Are Wrong

Option A: 60 days

60 days is too short and does not reflect the actual statutory requirement under Florida Statute 713.08

Option C: 120 days

120 days exceeds the statutory deadline and would result in an invalid lien filing

Option D: 180 days

180 days is far beyond the statutory requirement and represents a different timeline used for other construction-related deadlines

Memory Technique

Think '90 days to CLAIM your lien' - the word CLAIM helps you remember this is specifically for the Claim of Lien recording deadline

Reference Hint

Florida Statutes Chapter 713 - Construction Liens, specifically Section 713.08

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing