Under Florida Statute Chapter 713, how many days does a contractor have to record a claim of lien after the last day of work or delivery of materials?
Correct Answer
D) 90 days
Florida Statute 713.08 requires that a claim of lien must be recorded within 90 days after the last day the lienor performed labor or furnished materials. This is a strict deadline that cannot be extended.
Why This Is the Correct Answer
Florida Statute 713.08 specifically mandates that a claim of lien must be recorded within 90 days after the last day the lienor performed labor or furnished materials. This 90-day period is a strict statutory deadline that begins running from the final day of work or material delivery. The statute provides no exceptions or extensions to this timeframe, making it critical for contractors to track their final work dates carefully. Missing this deadline results in the complete loss of lien rights, regardless of the amount owed.
Why the Other Options Are Wrong
Option A: 30 days
30 days is too short and does not align with Florida Statute 713.08, which specifically requires 90 days for recording a claim of lien.
Option B: 45 days
45 days is insufficient time under Florida law and conflicts with the statutory requirement of 90 days established in Florida Statute 713.08.
Option C: 60 days
60 days falls short of the required timeframe and does not comply with Florida Statute 713.08's mandate of 90 days for recording lien claims.
Memory Technique
Think '90 days = 3 months = 1 quarter year' - Florida gives you a full business quarter to get your lien paperwork filed after your last day of work.
Reference Hint
Florida Statutes Chapter 713 - Construction Liens, specifically Section 713.08 regarding time limitations for recording claims of lien
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass