EstatePass
Contract AdminContractsmedium40% of exam part

Under Florida Statute Chapter 713, a Notice to Owner must be served within how many days after the lienor first furnishes labor, services, or materials to the property?

Correct Answer

D) 45 days

Florida Statute 713.06 requires that a Notice to Owner be served within 45 days after the lienor first furnishes labor, services, or materials to the property. This is a critical deadline for preserving lien rights.

Answer Options
A
60 days
B
30 days
C
90 days
D
45 days

Why This Is the Correct Answer

Florida Statute 713.06 specifically mandates that a Notice to Owner must be served within 45 days after the lienor first furnishes labor, services, or materials to the property. This 45-day deadline is absolute and critical for preserving lien rights under Florida's construction lien law. Failure to serve this notice within the prescribed timeframe can result in the complete loss of lien rights, regardless of the amount owed or quality of work performed. The statute is very strict about this timing requirement and does not provide exceptions for delays.

Why the Other Options Are Wrong

Option A: 60 days

60 days exceeds the statutory requirement and would be too late to preserve lien rights under Florida law

Option B: 30 days

90 days is far beyond the statutory deadline and would result in forfeiture of lien rights

Memory Technique

Think '45 to Stay Alive' - you have 45 days to serve Notice to Owner to keep your lien rights alive

Reference Hint

Florida Statutes Chapter 713 - Construction Liens, specifically Section 713.06 regarding Notice to Owner requirements

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.