Under Florida Statute Chapter 713, a Notice to Owner must be served within how many days after the lienor first furnishes labor, services, or materials to the property?
Correct Answer
B) 45 days
Florida Statute 713.06 requires that a Notice to Owner be served within 45 days after the lienor first furnishes labor, services, or materials to the property. This is a critical deadline for preserving lien rights.
Why This Is the Correct Answer
Florida Statute 713.06 specifically mandates that a Notice to Owner must be served within 45 days after the lienor first furnishes labor, services, or materials to the property. This 45-day deadline is absolute and critical for preserving lien rights under Florida's construction lien law. Failure to serve this notice within the prescribed timeframe can result in the complete loss of lien rights, regardless of the amount owed or quality of work performed. The statute is very strict about this timing requirement and does not provide exceptions for delays.
Why the Other Options Are Wrong
Option A: 30 days
30 days is too short and not the timeframe specified in Florida Statute 713.06 for Notice to Owner requirements
Option C: 60 days
60 days exceeds the statutory requirement and would be too late to preserve lien rights under Florida law
Option D: 90 days
90 days is far beyond the statutory deadline and would result in forfeiture of lien rights
Memory Technique
Think '45 to Stay Alive' - you have 45 days to serve Notice to Owner to keep your lien rights alive
Reference Hint
Florida Statutes Chapter 713 - Construction Liens, specifically Section 713.06 regarding Notice to Owner requirements
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass