Under Florida Statute Chapter 713, a contractor must serve a Notice to Owner within how many days of first furnishing labor, services, or materials to the improvement?
Correct Answer
A) 45 days
Florida Statute 713.06 requires contractors to serve a Notice to Owner within 45 days of first furnishing labor, services, or materials to preserve lien rights.
Why This Is the Correct Answer
Florida Statute 713.06 specifically requires contractors to serve a Notice to Owner within 45 days of first furnishing labor, services, or materials to an improvement. This notice is crucial for preserving lien rights under Florida's construction lien law. The 45-day timeframe is mandatory and begins from the date of first providing work or materials to the project, not from contract signing or project completion.
Why the Other Options Are Wrong
Option B: 30 days
30 days is too short and does not comply with Florida Statute 713.06. This timeframe might be confused with other construction-related notice requirements, but the Notice to Owner specifically requires 45 days. Using 30 days would result in failure to preserve lien rights if the notice is served between days 31-45.
Option C: 90 days
90 days exceeds the statutory requirement and would be unnecessarily long. While serving the notice within 90 days would still preserve lien rights (since it's within the 45-day requirement), Florida law specifically mandates 45 days. This longer timeframe might be confused with other construction statute deadlines.
Option D: 60 days
60 days is longer than the required 45-day period under Florida Statute 713.06. While serving within 60 days would preserve lien rights, the statute specifically requires 45 days. This timeframe might be confused with other notice periods in construction law or payment requirements.
Memory Technique
Remember '45 for Alive' - your lien rights stay alive if you serve Notice to Owner within 45 days of first furnishing work.
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
