Under Florida Statute 489.119, what happens to a contractor's license if they are found guilty of abandoning a construction project?
Correct Answer
C) Disciplinary action including possible suspension or revocation
Florida Statute 489.119 provides for disciplinary actions including suspension or revocation for abandoning projects, as this is considered a serious violation affecting public welfare.
Why This Is the Correct Answer
Florida Statute 489.119 specifically addresses disciplinary actions for contractors who abandon construction projects. Project abandonment is considered a serious violation that can harm property owners and the public welfare. The statute grants the Construction Industry Licensing Board broad disciplinary authority, including the power to suspend or revoke licenses for such violations. This reflects the severity with which Florida treats project abandonment as it can leave property owners with incomplete work and financial losses.
Why the Other Options Are Wrong
Option A: Automatic license suspension for 30 days
While suspension is possible under disciplinary action, there is no automatic 30-day suspension specified in the statute. The disciplinary process involves investigation and hearings, and penalties can range from lesser sanctions to complete revocation depending on the circumstances.
Option B: Mandatory continuing education requirement
Mandatory continuing education alone is insufficient for the serious violation of project abandonment. While additional education might be part of a disciplinary action, it would not be the primary or sole consequence for such a significant breach of professional responsibility.
Option D: Fine only, with license remaining active
A fine-only penalty with an active license would be inadequate for project abandonment cases. This serious violation threatens public welfare and property owner interests, requiring more substantial disciplinary measures than monetary penalties alone.
Memory Technique
Think 'ABANDON = SERIOUS' - abandoning projects is serious enough to abandon your license (suspension/revocation)
Reference Hint
Florida Statutes Chapter 489, specifically Section 489.119 - Disciplinary Actions and Penalties
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass