Under Florida Statute 489, which of the following can qualify as experience for General Contractor licensure?
Correct Answer
B) Experience in construction management or supervision
Florida Statute 489 recognizes construction management and supervision experience as qualifying experience for General Contractor licensure. This includes hands-on construction work, project management, and supervisory roles in construction.
Why This Is the Correct Answer
Florida Statute 489 specifically recognizes construction management and supervision experience as qualifying experience for General Contractor licensure. This includes direct involvement in construction projects through hands-on work, project management roles, and supervisory positions. The statute values practical construction experience that demonstrates knowledge of building processes, safety protocols, and project coordination. Construction management and supervision directly relate to the core responsibilities of a general contractor.
Why the Other Options Are Wrong
Option A: Experience as a real estate agent
Real estate agent experience does not qualify because it involves property sales and transactions rather than actual construction work, management, or supervision of building projects.
Option C: Experience as a building inspector only
Building inspector experience alone is insufficient because while it involves knowledge of codes and regulations, it lacks the hands-on construction management and supervisory experience required for general contractor licensure.
Option D: Experience as an architect without construction involvement
Architectural experience without construction involvement does not qualify because it focuses on design and planning rather than the practical construction management and supervision skills required for general contractor work.
Memory Technique
Think 'BUILD to QUALIFY' - only experience that involves actually BUILDing, managing, or supervising construction will QUALIFY under Florida Statute 489.
Reference Hint
Florida Statute 489 - Chapter on Contractor Licensing Requirements and Experience Qualifications
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
A concrete slab requires 250 cubic yards of concrete. If concrete costs $120 per cubic yard delivered, and there is typically 3% waste factor, what is the total material cost for concrete?
Next Question
A contractor is estimating labor costs for installing 2,000 square feet of ceramic tile. The productivity rate is 25 square feet per hour, and the labor rate is $32 per hour. What is the total labor cost?