Under Florida lien law, what is the maximum time period after recording a Claim of Lien that a lienor has to file a lawsuit to foreclose the lien?
Correct Answer
C) 1 year
Florida Statute 713.22 requires that a lawsuit to foreclose a construction lien must be filed within one year after recording the Claim of Lien, or the lien becomes void and unenforceable.
Why This Is the Correct Answer
Florida Statute 713.22 specifically mandates that a lawsuit to foreclose a construction lien must be commenced within one year after the Claim of Lien is recorded. This one-year deadline is absolute and non-negotiable - failure to file the foreclosure lawsuit within this timeframe renders the lien void and unenforceable. The statute was designed to provide a reasonable but definitive time limit to prevent liens from remaining as clouds on title indefinitely while still giving lienors adequate time to pursue their legal remedies.
Why the Other Options Are Wrong
Option A: 60 days
60 days is too short and does not align with Florida Statute 713.22, which provides a much longer period for lienors to initiate foreclosure proceedings.
Option B: 90 days
90 days is insufficient time under Florida law and conflicts with the statutory requirement of one year established in Florida Statute 713.22.
Option D: 2 years
2 years exceeds the statutory time limit and would allow liens to cloud property titles for an unreasonably long period, which goes against the legislative intent of Florida Statute 713.22.
Memory Technique
Think 'One Claim, One Year' - once you record your Claim of Lien, you have exactly one year to take legal action or lose your lien rights forever.
Reference Hint
Florida Building Construction Standards - Chapter 713 Construction Liens, specifically Section 713.22
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass