EstatePass
Contract AdminContractshard40% of exam part

Under Florida lien law, if a Notice to Owner is not properly served, what is the consequence for the potential lienor?

Correct Answer

B) Lien rights are lost entirely

Under Florida Chapter 713, failure to properly serve a Notice to Owner within the required timeframe results in the complete loss of lien rights. The Notice to Owner is a prerequisite for maintaining lien rights on private projects.

Answer Options
A
The lien amount is limited to the last 30 days of work
B
Lien rights are lost entirely
C
The lien filing period is extended to 120 days
D
The lien is valid but has lower priority

Why This Is the Correct Answer

Under Florida Chapter 713, failure to properly serve a Notice to Owner within the required timeframe results in the complete loss of lien rights. The Notice to Owner is a prerequisite for maintaining lien rights on private projects.

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing