Under Florida lien law, if a lienor fails to file a lawsuit to enforce their lien within the required timeframe, what happens to the lien?
Correct Answer
B) The lien automatically becomes null and void
Florida Statute 713.22 requires that a lawsuit to enforce a lien must be filed within one year after recording the lien. Failure to file suit within this timeframe causes the lien to automatically become null and void.
Why This Is the Correct Answer
Florida Statute 713.22 establishes a strict one-year deadline for filing a lawsuit to enforce a construction lien after it has been recorded. This is a mandatory timeframe with no exceptions or extensions. When a lienor fails to file the enforcement lawsuit within this one-year period, the lien automatically loses all legal effect and becomes completely null and void. The statute provides no mechanism for partial validity or reduced enforcement - it's an all-or-nothing requirement.
Why the Other Options Are Wrong
Option A: The lien remains valid but cannot be enforced
Option A is incorrect because a lien cannot remain valid but unenforced under Florida law. The statute creates a binary outcome - either the lien is fully valid and enforceable, or it becomes completely null and void. There is no middle ground where a lien maintains validity without enforceability.
Option C: The lien amount is reduced by 50%
Option C is incorrect because Florida lien law does not provide for any reduction in lien amounts based on timing failures. The statute operates on an all-or-nothing basis - the full lien either remains valid or becomes completely void, with no provision for partial amounts or percentage reductions.
Option D: The lien can be renewed for another year
Option D is incorrect because Florida Statute 713.22 does not allow for renewal or extension of the one-year enforcement deadline. Once the one-year period expires without filing suit, the lien is permanently void and cannot be revived, renewed, or extended under any circumstances.
Memory Technique
Think 'NULL and VOID in ONE' - if you don't file suit within ONE year, your lien becomes NULL and VOID completely
Reference Hint
Florida Statutes Chapter 713 - Construction Liens, specifically Section 713.22 regarding enforcement timeframes
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
Your project site is located in an area with endangered Florida scrub-jays. Construction activities are restricted during which time period?
Next Question
A subcontractor's indemnification clause states they will 'defend, indemnify and hold harmless the contractor from any claims arising from subcontractor's negligent acts.' If the subcontractor's employee is injured due to the subcontractor's safety violation, who is primarily responsible for the claim?